Stage |
Period |
|
Access arrangement works |
April - September 2006 |
|
Accommodation works |
April - September 2006 |
|
Landscaping works |
August - October 2006 |
|
General track maintenance |
February - October 2006 |
|
Reinstatement of parallel track |
April - October 2006 |
|
Rail level crossing upgrades |
April 2006 - late 2007 |
|
Overall project completion |
Late 2007 |
Preliminary works included an upgrade of Pelican Point Road (completed in May 2006), which will ensure that Pelican Point Road has the capacity to cater for the new Outer Harbor Grain Terminal and future development opportunities at Outer Harbor.