Schedule

Belair line

Below is a table of the estimated timing of major milestones for the Belair Line Renewal Project.

Activity  Timing
Award Design and Construct contract to successful tenderer January / February 2009
Detailed design At least 2 months
Start major construction works (Belair line closed) March / April 2009
Complete first stage of track upgrade Mid 2009

 